Construction
Construction

Hours of construction are Monday to Friday from 6am to 7pm and Saturday 7am to 4pm, unless modified or otherwise varied in accordance with the Conditions of Approval.

 

April - June 2009

Construction activities in April, May and June 2009 included:

  • Transportation of quarry materials.
  • Earthworks and drainage works.
  • Bridge construction.
  • Pavement works.
  • Operation of concrete batch plants.
  • Landscaping and finishing works.

January - March 2009

Construction activities in January, February and March are currently scheduled to include:

  • Transportation of quarry material.
  • Earthworks and drainage works.
  • Bridge demolition and construction.
  • Pavement works.
  • Operation of concrete batch plants.
  • Landscaping.

October - December 2008

Construction activities in October, November and December 2008 included:

  • Clearing and mulching vegetation.
  • Installing environmental controls.
  • Transporting quarry material.
  • Earthworks and drainage works.
  • Bridgeworks.
  • Establishing and operating concrete batch plants.

July - September 2008

Construction activities in July, August and September 2008 included:

  • Clearing and mulching vegetation.
  • Installing envrionmental controls.
  • Relocating electricitity and telephone utilities.
  • Transporting quarry material.
  • Earthworks and drainage works.
  • Establishing and operating a concrete batch plant.

April - June 2008

Constrcution activities in April, MAy and June 2008 included:

  • Clearing and mulching vegetation.
  • Installing environmental controls.
  • Relocating electricity and telephone utilities.
  • Transporting fill material.
  • Earthworks and drainage works.
  • Bridgeworks including piling.
  • Blasting.
  • Pavement works.

January - March 2008

Construction activites in January, February and March 2008 included:

  • Installation of environmental controls.
  • Fencing, site establishment and utility relocations.
  • Clearing and mulching vegetation.
  • Stripping topsoil for future reuse.
  • Earthworks (including some haulage by road) and bridgeworks.
  • Installing stormwater drainage.
  • Temporary and permanent pavement works adjacent to the highway.

October - December 2007

Construction activites on the Hume Highway south of Mullengandra to Table Top in October, November and December 2008 included:

  • Installation of environmental controls.
  • Fencing, site establishment and utility relocations.
  • Topsoil stripping, preliminary earthworks and transportation of fill material off site.
  • Drainage and pavement works.

April – September 2007

Preliminary construction works from south of the Olympic Highway (Bells Road) to Tynan Road at Table Top are currently scheduled commenced in mid April 2007. The construction activities include:

  • Fencing, site establishment and utility relocations.
  • Clearing and earthworks.